Key Elements of Development
As of October 2026
A practical list for Iowa supervisors and planning commissions writing a data center ordinance. Each item is a question the ordinance should answer. The examples are from adopted Iowa county texts. They are illustrations, not a model code.
Where data centers are allowed
Say whether a data center is a listed use, a conditional use, or its own district, and in which parts of the unincorporated county. Linn County created an EU-3 district for large-scale centers. Osceola County allows them as a permitted use in its GI district. Allamakee County allows a micro center, 3 megawatts or less, with a permit in several districts, and a larger one only as a conditional use in I-2.
Setbacks and buffers
Set the distance from homes, schools, and property lines, and say who can reduce it. Linn County uses 200 feet to a property line and 1,000 feet from a home-zoned lot or a place of public assembly, unless the board reduces that with the affected city.
Noise
Set a number, say where it is measured, and say when backup generators may be tested. Linn County uses an average hourly limit of 55 dBA or 65 dBC at the wall of an occupied home. Greene County's amendment uses a 65 dB daily average for data centers and cryptocurrency operations.
Water
Ask where the water comes from, how much the design will use, and how use will be reported in a dry year. Linn County requires a water study and a water-use agreement for large projects. Clinton County requires closed-loop liquid cooling and a water-use impact statement. Allamakee County bans groundwater or surface water for cooling.
Power and the utility
Ask the applicant to show that the utility can serve the load, including substations and lines, before the county approves the site. Linn County requires written verification from the power provider. Jefferson County asks for grid interconnection points on the site plan.
Backup generators and air permits
Ask for the fuel, the number and size of generators, how often they will be tested, and which air permits apply. Linn County requires that backup-power plan, including emission controls, and compliance with local, state, and federal permits.
Lighting and screening
Ask for fixture type, mounting height, and light at the property line. Linn County and Jefferson County both require full-cutoff fixtures so light does not shine upward or onto neighboring property. Jefferson also asks for steps to limit glare.
Stormwater and the site plan
Require a site plan that shows buildings, access, drainage, and utilities, plus a stormwater pollution prevention plan. Linn County requires that plan, an erosion-control plan, and a permanent foundation under the computing equipment.
Roads and construction traffic
Identify the haul routes, record road condition before work starts, and say who pays for damage. Linn County requires a road-use agreement before construction. Jefferson County's agreement can cover dust, overweight loads, and a bond or letter of credit for the roads.
Decommissioning and financial assurance
Say when a closed building must come out, what the site is restored to, and what security covers the cost. Jefferson County requires a decommissioning plan with a cost estimate and a bond, letter of credit, escrow, or similar assurance, reviewed at least every five years.
Development agreements and community benefits
Decide which payments or community commitments are conditions of approval, and what happens if the jobs or investment do not show up. Linn County requires an economic development agreement for large projects, along with the water agreement.
Public notice and hearings
Say who gets mailed notice, how far out, and whether a neighborhood meeting is required before the planning commission. Linn County requires notice to owners and tenants within 1,000 feet, and a public information meeting before the commission hearing. Jefferson County requires notice to a city if the site is within two miles of city limits.