Iowa County Data Center Planning and Zoning Ordinances
As of October 2026
Adair County
Moratorium in effect · Proposed
Resolution #2026-26 imposed a temporary moratorium on data centers, high-density computing and battery storage facilities. Proposed Ordinance 41 (siting, construction, operation and decommissioning of data centers and crypto mining) had its first reading and public hearing on 2026-09-23, with the next hearing set for 2026-10-14.
Latest update: September 23, 2026
Adams County
Moratorium in effect
Resolution 2026-25 imposes a 24-month moratorium on approving new rezonings and other approvals for data center facilities in unincorporated Adams County while Land Use Code amendments are drafted.
June 15, 2026
Allamakee County
Ordinance adopted
Amendment #20 to Zoning Ordinance L regulates data centers: micro data centers (3 MW or less) are allowed in A-1, C-1, I-1 and I-2 with a permit, and large data centers (over 3 MW) only as a conditional use in I-2. It bans groundwater or surface water for cooling and sets spacing and setback rules.
April 13, 2026
Appanoose County
No data center ordinance found.
Audubon County
Moratorium in effect
Resolution 2026-27 sets a temporary moratorium on accepting or processing applications for commercial data centers, including crypto mining, until 2027-05-01 or until a permanent ordinance is adopted.
May 5, 2026
Benton County
No data center ordinance found.
Black Hawk County
No data center ordinance found.
Boone County
Moratorium in effect
Resolution 26-36 adopts a moratorium of up to one year on establishing, constructing or permitting new data centers while the county studies and drafts a comprehensive data center zoning ordinance.
September 9, 2026
Bremer County
No data center ordinance found.
Buchanan County
Moratorium in effect
The board extended its moratoriums on commercial data mining facilities and data storage centers (first adopted early 2026) while Planning and Zoning drafts ordinances; aggregator data lists the extension through 2027-12-31.
May 18, 2026
Buena Vista County
No data center ordinance found.
Butler County
No data center ordinance found.
Calhoun County
No data center ordinance found.
Carroll County
No data center ordinance found.
Cass County
No data center ordinance found.
Cedar County
Moratorium in effect
The board approved a six-month moratorium on data centers while staff and county attorneys finish a data center ordinance. A proposed ordinance regulating data center placement was on the 2026-09-22 agenda to set public hearing dates.
May 26, 2026
Cerro Gordo County
No data center ordinance found.
Cherokee County
No data center ordinance found.
Chickasaw County
No data center ordinance found.
Clarke County
Moratorium in effect
Resolution #25-011 establishes a temporary moratorium on building data centers in unincorporated Clarke County. It lasts until the board adopts a permanent moratorium or data center ordinances, or rescinds it.
June 23, 2025
Clay County
No data center ordinance found.
Clayton County
Moratorium in effect · Proposed
A moratorium on rezonings and conditional use permits for digital asset mining and data centers (Res #8-2025, 2025-02-25) was extended on 2025-12-02 through 2026-12-31. Planning and Zoning is still revising draft data center ordinances.
Latest update: September 22, 2026
Clinton County
Ordinance adopted
Ordinance 2025-06 adds zoning Sec. 4.2.21 Data Centers. Data centers are allowed only by special exception permit in C-1, C-2, M-1 and M-2, and must use a closed-loop liquid cooling system, file a water-use impact statement and submit a decommissioning plan.
December 1, 2025
Crawford County
Under revision
On 2026-09-22 the board discussed a proposed data center ordinance with the county attorney and WIPCO; no action was taken.
Date not confirmed
Dallas County
Ordinance adopted
The Chapter 45 zoning ordinance lists data centers as a permitted principal use in the I-1 Light Industrial District. No data-center-specific standards were found.
Date not confirmed
Davis County
No data center ordinance found.
Decatur County
No data center ordinance found.
Delaware County
No data center ordinance found.
Des Moines County
Moratorium in effect · Proposed
Resolution #2026-034 imposes a one-year moratorium on accepting or approving permit applications for data centers, including commercial crypto mining, while the county develops siting and operating regulations.
Latest update: September 22, 2026
Dickinson County
Moratorium in effect
Resolution 2026-8 imposes a six-month moratorium on permits for data centers, Bitcoin mining, solar and battery storage facilities while the county updates its comprehensive land use plan.
May 12, 2026
Dubuque County
Moratorium in effect · Proposed
The signed resolution sets a moratorium on small, medium, large-scale and hyperscale data centers through 2027-05-26 (replacing #26-107 of 2026-05-26) while the county plans. A draft data center ordinance was released in August 2026.
Latest update: September 22, 2026
Emmet County
Moratorium in effect
Resolution 26-25 imposes a one-year moratorium on new data center development in unincorporated Emmet County while the county studies impacts and develops regulations.
August 25, 2026
Fayette County
Moratorium in effect
The board placed a temporary moratorium, through 2027-12-31, on rezonings and conditional use permits for digital asset mining and data centers.
March 9, 2026
Floyd County
Moratorium in effect
Resolution #07-26 imposes a one-year moratorium (to 2027-03-02) on conditional use and zoning applications for data centers, including cryptocurrency operations.
March 3, 2026
Franklin County
Moratorium in effect
Ordinance 2026A authorizes a moratorium on new permit applications for data center projects in unincorporated Franklin County. It was adopted with the first and second readings waived.
March 31, 2026
Fremont County
No data center ordinance found.
Greene County
Ordinance adopted
A zoning ordinance amendment sets conditional use permit conditions for data centers and cryptocurrency operations, including a 65 dB daily average noise limit, a 15,000 gallon/month water cap, utility tariff verification and site restoration.
December 22, 2025
Grundy County
Moratorium in effect
Resolution #46-2024/2025 imposes an indefinite moratorium on special exception permits for data processing centers in M (industrial) zoning districts.
April 2025
Guthrie County
No data center ordinance found.
Hamilton County
No data center ordinance found.
Hancock County
Proposed
After a moratorium was tabled on 9/21 and failed for lack of a second on 9/28, Supervisor Rayhons presented a zoning amendment that would make data centers conditional uses, to be considered at the board's next meeting (reported by KIOW on 2026-10-06).
Date not confirmed
Hardin County
No data center ordinance found.
Harrison County
No data center ordinance found.
Henry County
Moratorium in effect
The board approved a moratorium, effective noon 2026-05-14 through 2026-12-31, on new siting applications for AI data centers, data mines and battery energy storage systems while it drafts policy.
May 14, 2026
Howard County
No data center ordinance found.
Humboldt County
No data center ordinance found.
Ida County
Moratorium in effect · Proposed
Resolution 26-30 enacts a moratorium on new data center development until the board lifts it. A first draft of a permanent data center ordinance was shared in September 2026.
Latest update: September 29, 2026
Iowa County
Moratorium in effect
Resolution 2026-07-31 imposes a 12-month moratorium on accepting, processing and approving applications for all classes of data centers in the unincorporated county.
July 31, 2026
Jackson County
Moratorium in effect · Proposed
Resolution #1205-08-04-2026 extends and updates the temporary moratorium on high-density computing and data processing facilities in unincorporated Jackson County until 2027-08-04.
Latest update: August 17, 2026
Jasper County
No data center ordinance found.
Jefferson County
Moratorium in effect · Ordinance adopted · Under revision
The board adopted a Chapter 5-45 data center ordinance (permits approved by Board resolution under home rule) and a 12-month moratorium on data center permits.
Reported September 14, 2026
Johnson County
Moratorium in effect · Proposed
Resolution 11-06-25-01 imposes a temporary moratorium on data center rezoning, subdivision, site plan and building permit applications in unincorporated Johnson County through 2026-11-08. Supervisors were expected to consider an extension in October 2026.
Latest update: September 2, 2026
Jones County
Ordinance adopted
Ordinance 2025-02 replaces zoning Article XVIII with 'Cryptocurrency and Data Centers.' These facilities need site plan review and a special use permit in specified districts.
May 13, 2025
Keokuk County
No data center ordinance found.
Kossuth County
No data center ordinance found.
Lee County
Moratorium in effect · Proposed
Resolution 2026-76 imposes a one-year moratorium on building new data centers (large, small and high-density) while the county researches impacts and drafts an ordinance.
Latest update: October 6, 2026
Linn County
Moratorium in effect · Ordinance adopted · Under revision
A data center ordinance approved 2026-02-18 created an EU-3 Large-Scale Data Center District plus small and large data center standards (water study, water use agreement, economic development agreement). An 18-month moratorium on EU-3 rezoning applications took effect 2026-07-01 and runs through 2028-01-01.
Latest update: August 10, 2026
Louisa County
Moratorium in effect
Ordinance 26-1 imposes an 18-month moratorium on data center development in unincorporated Louisa County, or until a regulating ordinance is adopted. The second and third readings were waived.
July 7, 2026
Lucas County
Moratorium in effect
The board adopted a one-year moratorium on permitting, constructing or vesting data centers, including cryptocurrency operations.
August 5, 2026
Lyon County
Moratorium in effect
Resolution 2026-24 adopts a temporary moratorium on data centers in the county.
September 22, 2026
Madison County
Moratorium in effect
The board approved a 12-month moratorium on new data center projects (second and third readings waived) while it revises data center zoning rules.
May 26, 2026
Mahaska County
Moratorium in effect · Proposed
The board adopted a one-year data center moratorium and formed a 7-member study committee, which was drafting a data center ordinance as of late September 2026.
Latest update: September 29, 2026
Marion County
Moratorium in effect
A moratorium on data processing centers, crypto mining, and battery storage was adopted June 23, 2026, and runs through July 1, 2027, so the zoning commission can draft regulations.
Latest update: June 23, 2026
Marshall County
Moratorium in effect
The board voted 3-0 for a six-month moratorium resolution on new applications for data centers, AI computing, data mining and cryptocurrency mining in unincorporated areas while the Zoning Commission drafts regulations.
September 23, 2026
Mills County
No data center ordinance found.
Mitchell County
Moratorium in effect
Resolution #1336-25 establishes a moratorium on data centers until 2026-12-31 while guidelines are developed.
November 25, 2025
Monona County
Ordinance adopted
Ordinance No. 71 adds a 'Digital Currency Mining and/or Data Center Facility' definition and new zoning Sec. 100.37, which requires site plan review and special use approval in listed districts, plus noise, emergency and decommissioning standards.
March 11, 2025
Monroe County
No data center ordinance found.
Montgomery County
No data center ordinance found.
Muscatine County
Ordinance adopted
Ordinance #05-12-25-01 defines 'Cryptocurrency mining or production installations and Data Center' and makes it a Special Permitted Use in the I-1 and I-2 districts. In June 2026 the board asked staff to review it.
May 12, 2025
O'Brien County
Moratorium in effect
Resolution 2026-17 adopts a data center moratorium through 2026-12-31.
May 19, 2026
Osceola County
Ordinance adopted
Ordinance No. 66 adds a Data Center definition (covering cloud, cryptocurrency and AI facilities) to the zoning ordinance and makes data centers a principal permitted use in the GI district.
June 9, 2026
Page County
Moratorium in effect
On a 2-1 vote the board approved a temporary data center moratorium, which can be rescinded at any time, while it reviews existing ordinances.
July 21, 2026
Palo Alto County
Moratorium in effect
Resolution No. 7-8-2026 approves a moratorium on accepting, processing and approving applications for all classes of data centers in unincorporated Palo Alto County.
July 7, 2026
Plymouth County
Moratorium in effect · Proposed
The board unanimously approved a one-year, revocable moratorium on permitting large-scale data centers and industrial battery storage facilities.
Reported September 2, 2026
Pocahontas County
No data center ordinance found.
Polk County
No data center ordinance found.
Pottawattamie County
No data center ordinance found.
Poweshiek County
Moratorium in effect
On a 2-1 vote the board approved Resolution 2027-11, a temporary moratorium on accepting, processing and approving applications for all classes of data centers in unincorporated Poweshiek County. It runs until 2027-09-27 or until zoning amendments regulating data centers are adopted.
September 28, 2026
Ringgold County
Moratorium in effect
The board adopted a 12-month data center moratorium ordinance (third reading waived; Resolution RC26.106) and plans to draft a permanent ordinance.
July 6, 2026
Sac County
Moratorium in effect
Resolution 25-0204-2 (2025-02-04) set a moratorium on conditional use permits for digital asset mining and data centers. It was extended on 12/9/2025 and again by Resolution S2026-0509E through 2026-12-31.
June 9, 2026
Scott County
No data center ordinance found.
Shelby County
Moratorium in effect
Resolution 2026-16 imposes a moratorium on commercial digital asset mining and data centers in unincorporated Shelby County while an ordinance is developed; aggregator data lists it through 2027-07-01.
March 17, 2026
Sioux County
Moratorium in effect · Proposed
A data center moratorium is in place (aggregator data: Res 2026-32, 2026-06-16). An amendment to County Ordinance No. 1 adding data center regulations passed first reading on 2026-09-29, with second and third readings set for 10/13 and 10/27.
Latest update: September 29, 2026
Story County
Moratorium in effect
Resolution #26-69 extends the temporary moratorium on applications and permits for digital asset mining, cryptocurrency operations and data processing centers in unincorporated Story County through 2027-03-31.
March 17, 2026
Tama County
Moratorium in effect
Resolution 11-10-2025A imposes an indefinite moratorium on new data mining and data center developments until a land use plan and a data center ordinance are adopted.
November 10, 2025
Taylor County
Moratorium in effect
Temporary moratorium Ordinance (No. 40 per aggregator and news reports) covers data center development and other uses, including solar and battery storage, for 12 months.
July 30, 2026
Union County
Moratorium in effect
The board approved an up-to-one-year moratorium on new data centers and other high-density facilities and created a data center study committee (aggregator data: Res #21 FYR 25/26, 2026-03-25).
Reported March 30, 2026
Van Buren County
No data center ordinance found.
Wapello County
Proposed
County officials are drafting a data center ordinance.
Latest update: September 15, 2026
Warren County
Ordinance adopted
The new zoning ordinance (Res 25-323) defines 'Data Center' and allows it only as a conditional use in the HI district. Standards include liquid cooling, concrete foundations, a 75 ft separation from residential, noise limits of 60 dB day / 50 dB night, utility capacity verification and decommissioning.
December 16, 2025
Washington County
No data center ordinance found.
Wayne County
No data center ordinance found.
Webster County
No data center ordinance found.
Winnebago County
Under revision
County officials are drafting zoning ordinance updates covering solar, crypto, battery storage and data center facilities.
Date not confirmed
Winneshiek County
Moratorium in effect
Resolution 27-10 adopts a 12-month moratorium on data center rezoning, permits and construction.
September 28, 2026
Woodbury County
Moratorium in effect · Proposed
Resolution 14064 imposes a 12-month moratorium on accepting, processing and approving applications for all classes of data centers in unincorporated Woodbury County.
Latest update: September 21, 2026
Worth County
No data center ordinance found.
Wright County
No data center ordinance found.