City News and Ordinances

As of October 2026

  1. AltoonaPolk County

    Adopted

    Council voted 4-0 to rezone 15 more acres from agricultural to conditional limited industrial for IALCO Polk County Four (Tract) data center development, matching conditions on the 373 acres rezoned in June 2025.

    Latest news: February 16, 2026

  2. AmesStory County

    In progress

    After strong opposition, the council delayed Lightedge's proposed data center near the airport until May 2027 and adopted a 12-step review covering zoning, ordinance and noise changes. A new 15-member committee studying environmental impacts reports to the council by Feb. 28, 2027.

    Latest news: September 25, 2026

  3. BooneBoone County

    Under consideration

    Lightedge has a letter of intent with the Boone County Economic Growth Corp. for 10 acres in the Boone Business Park for a small colocation data center. No site plan has been filed yet, but the proposal has dominated public comment at recent council meetings.

    Latest news: October 6, 2026

  4. Cedar RapidsLinn County

    Adopted

    Two hyperscale data centers (Google and QTS) are under construction with 15-year tax breaks and community betterment funds, and a third, smaller data center has been permitted. The mayor publicly defended the projects against water, rate and transparency concerns.

    Latest news: July 23, 2026

  5. Center PointLinn County

    In progress

    At a joint council and planning and zoning work session, leaders gave staff direction to draft a permanent data center ordinance modeled on Linn County's, before any developer has approached the city. Planning and zoning is set to review the draft in October.

    Latest news: September 29, 2026

  6. Central CityLinn County

    In progress

    The city put a moratorium in place and is drafting an ordinance after Aurum proposed the 18,000-square-foot, 4 MW Elk Data Center near the Linn County Fairgrounds. Residents packed a public meeting with questions.

    Latest news: September 30, 2026

  7. ClintonClinton County

    In progress

    After rejecting a moratorium in June, the council has spent months drafting a data center zoning ordinance (Section 159.033) as QTS is under contract for about 1,100 acres. A public hearing on the ordinance is set for Oct. 8, 2026.

    Latest news: October 3, 2026

  8. Council BluffsPottawattamie County

    Under consideration

    The council unanimously rejected the mayor's proposed one-year moratorium on new data centers. Instead it favored a wastewater management plan and case-by-case review, and possible zoning updates, as the city nears sewer capacity.

    Latest news: June 16, 2026

  9. DavenportScott County

    Adopted

    The city approved property tax incentives in 2024 (a 60% exemption for 20 years) for Meta's Vemerald data center on 355 acres in north Davenport. As of early 2026 the project had not broken ground and Meta had not announced plans to build.

    Latest news: February 25, 2026

  10. DubuqueDubuque County

    Adopted

    The council adopted a six-month moratorium on hyperscale data centers (100,000+ sq ft, 75+ MW, 5,000+ servers or 50+ gpm water) and directed the city attorney to draft a long-term data center ordinance.

    Latest news: September 22, 2026

  11. FairfaxLinn County

    In progress

    The council voted 3-1 to advance an open-ended moratorium on high-impact data centers (10+ MW) pending attorney review and further readings, while planning and zoning drafts a data center zoning ordinance. Construction traffic from the Cedar Rapids data center sites is a major local concern.

    Latest news: July 15, 2026

  12. FairfieldJefferson County

    Adopted

    The council voted 6-0 to adopt a 12-month moratorium on data center construction, waiving the second and third readings, while the city evaluates regulations. The mayor proposed a data center task force.

    Latest news: August 26, 2026

  13. Fort MadisonLee County

    In progress

    After a proposed AI data center at Burlington Hill, just outside city limits, was halted by a Lee County moratorium and a cease-and-desist order, the planning and zoning commission is reviewing a High Infrastructure Impact Development ordinance and two-mile extraterritorial zoning.

    Latest news: October 1, 2026

  14. HullSioux County

    Under consideration

    PathOne Data Centers held a public meeting in Hull on a proposed 40,000-square-foot, 10 MW data center at the former Bison Renewable Energy site southwest of town. A Sioux County moratorium on unincorporated areas is in effect while the county drafts an ordinance.

    Latest news: August 25, 2026

  15. MarshalltownMarshall County

    In progress

    The council adopted a moratorium in August that runs through Nov. 23. The city is now finishing a data center ordinance with possible overlay districts in Edgewood Industrial Park and east of 18th Avenue, with a P&Z hearing Oct. 15 and first council reading targeted Oct. 26. Swarm Systems wants to build there.

    Latest news: October 2, 2026

  16. Mason CityCerro Gordo County

    Adopted

    In April 2026 the council rezoned roughly 380-400 acres on the southwest side to industrial use, which could include a data center. QTS has shown interest but no agreement or project has been approved. About 100 residents attended an Iowa CCI informational meeting on Sept. 29.

    Latest news: October 1, 2026

  17. NorwalkWarren County

    Adopted

    Despite heavy public opposition, the council approved an infrastructure development agreement with land developer IALCO Warren County Two (Tract) for a roughly 282-acre annexed data center site. The agreement does not approve a specific data center.

    Latest news: March 6, 2026

  18. PaloLinn County

    Adopted

    The council voted 4-1 to adopt a data center ordinance creating an EU-1 Data Center Exclusive Use zoning district. Google is weighing annexation of a 545-acre site near the Duane Arnold nuclear plant but has not filed an application.

    Latest news: July 21, 2026

  19. PeostaDubuque County

    Adopted

    The council unanimously extended its data center moratorium by six months, to June 18, 2027, to allow more time to review public feedback and write a technical data center zoning ordinance.

    Latest news: September 29, 2026

  20. SalixWoodbury County

    In progress

    Google is eyeing 900 acres annexed by Salix, an annexation Woodbury County is challenging in court. The council rejected a moratorium in August, has started drafting a data center ordinance, and will vote Oct. 14 on an agreement under which Google pays up to $150,000 for independent reviews.

    Latest news: October 1, 2026

  21. Sioux CityWoodbury County

    In progress

    The Planning and Zoning Commission will discuss data center zoning on Oct. 13 and review a draft amendment Oct. 27, with a recommendation to the council expected in November. The current code has no data center land-use category.

    Latest news: October 2, 2026

  22. WaterlooBlack Hawk County

    Adopted

    The council unanimously approved a three-month data center moratorium after protests over a December 2025 agreement with a data center developer for a 12-acre site that included tax breaks and a $1 land transfer. A six-month hyperscale pause is expected at a future meeting.

    Latest news: September 9, 2026