City News and Ordinances
As of October 2026
AltoonaPolk County
Adopted
Council voted 4-0 to rezone 15 more acres from agricultural to conditional limited industrial for IALCO Polk County Four (Tract) data center development, matching conditions on the 373 acres rezoned in June 2025.
Latest news: February 16, 2026
AmesStory County
In progress
After strong opposition, the council delayed Lightedge's proposed data center near the airport until May 2027 and adopted a 12-step review covering zoning, ordinance and noise changes. A new 15-member committee studying environmental impacts reports to the council by Feb. 28, 2027.
Latest news: September 25, 2026
BooneBoone County
Under consideration
Lightedge has a letter of intent with the Boone County Economic Growth Corp. for 10 acres in the Boone Business Park for a small colocation data center. No site plan has been filed yet, but the proposal has dominated public comment at recent council meetings.
Latest news: October 6, 2026
Cedar RapidsLinn County
Adopted
Two hyperscale data centers (Google and QTS) are under construction with 15-year tax breaks and community betterment funds, and a third, smaller data center has been permitted. The mayor publicly defended the projects against water, rate and transparency concerns.
Latest news: July 23, 2026
Center PointLinn County
In progress
At a joint council and planning and zoning work session, leaders gave staff direction to draft a permanent data center ordinance modeled on Linn County's, before any developer has approached the city. Planning and zoning is set to review the draft in October.
Latest news: September 29, 2026
Central CityLinn County
In progress
The city put a moratorium in place and is drafting an ordinance after Aurum proposed the 18,000-square-foot, 4 MW Elk Data Center near the Linn County Fairgrounds. Residents packed a public meeting with questions.
Latest news: September 30, 2026
ClintonClinton County
In progress
After rejecting a moratorium in June, the council has spent months drafting a data center zoning ordinance (Section 159.033) as QTS is under contract for about 1,100 acres. A public hearing on the ordinance is set for Oct. 8, 2026.
Latest news: October 3, 2026
Council BluffsPottawattamie County
Under consideration
The council unanimously rejected the mayor's proposed one-year moratorium on new data centers. Instead it favored a wastewater management plan and case-by-case review, and possible zoning updates, as the city nears sewer capacity.
Latest news: June 16, 2026
DavenportScott County
Adopted
The city approved property tax incentives in 2024 (a 60% exemption for 20 years) for Meta's Vemerald data center on 355 acres in north Davenport. As of early 2026 the project had not broken ground and Meta had not announced plans to build.
Latest news: February 25, 2026
DubuqueDubuque County
Adopted
The council adopted a six-month moratorium on hyperscale data centers (100,000+ sq ft, 75+ MW, 5,000+ servers or 50+ gpm water) and directed the city attorney to draft a long-term data center ordinance.
Latest news: September 22, 2026
FairfaxLinn County
In progress
The council voted 3-1 to advance an open-ended moratorium on high-impact data centers (10+ MW) pending attorney review and further readings, while planning and zoning drafts a data center zoning ordinance. Construction traffic from the Cedar Rapids data center sites is a major local concern.
Latest news: July 15, 2026
FairfieldJefferson County
Adopted
The council voted 6-0 to adopt a 12-month moratorium on data center construction, waiving the second and third readings, while the city evaluates regulations. The mayor proposed a data center task force.
Latest news: August 26, 2026
Fort MadisonLee County
In progress
After a proposed AI data center at Burlington Hill, just outside city limits, was halted by a Lee County moratorium and a cease-and-desist order, the planning and zoning commission is reviewing a High Infrastructure Impact Development ordinance and two-mile extraterritorial zoning.
Latest news: October 1, 2026
HullSioux County
Under consideration
PathOne Data Centers held a public meeting in Hull on a proposed 40,000-square-foot, 10 MW data center at the former Bison Renewable Energy site southwest of town. A Sioux County moratorium on unincorporated areas is in effect while the county drafts an ordinance.
Latest news: August 25, 2026
MarshalltownMarshall County
In progress
The council adopted a moratorium in August that runs through Nov. 23. The city is now finishing a data center ordinance with possible overlay districts in Edgewood Industrial Park and east of 18th Avenue, with a P&Z hearing Oct. 15 and first council reading targeted Oct. 26. Swarm Systems wants to build there.
Latest news: October 2, 2026
Mason CityCerro Gordo County
Adopted
In April 2026 the council rezoned roughly 380-400 acres on the southwest side to industrial use, which could include a data center. QTS has shown interest but no agreement or project has been approved. About 100 residents attended an Iowa CCI informational meeting on Sept. 29.
Latest news: October 1, 2026
NorwalkWarren County
Adopted
Despite heavy public opposition, the council approved an infrastructure development agreement with land developer IALCO Warren County Two (Tract) for a roughly 282-acre annexed data center site. The agreement does not approve a specific data center.
Latest news: March 6, 2026
PaloLinn County
Adopted
The council voted 4-1 to adopt a data center ordinance creating an EU-1 Data Center Exclusive Use zoning district. Google is weighing annexation of a 545-acre site near the Duane Arnold nuclear plant but has not filed an application.
Latest news: July 21, 2026
PeostaDubuque County
Adopted
The council unanimously extended its data center moratorium by six months, to June 18, 2027, to allow more time to review public feedback and write a technical data center zoning ordinance.
Latest news: September 29, 2026
SalixWoodbury County
In progress
Google is eyeing 900 acres annexed by Salix, an annexation Woodbury County is challenging in court. The council rejected a moratorium in August, has started drafting a data center ordinance, and will vote Oct. 14 on an agreement under which Google pays up to $150,000 for independent reviews.
Latest news: October 1, 2026
Sioux CityWoodbury County
In progress
The Planning and Zoning Commission will discuss data center zoning on Oct. 13 and review a draft amendment Oct. 27, with a recommendation to the council expected in November. The current code has no data center land-use category.
Latest news: October 2, 2026
WaterlooBlack Hawk County
Adopted
The council unanimously approved a three-month data center moratorium after protests over a December 2025 agreement with a data center developer for a 12-acre site that included tax breaks and a $1 land transfer. A six-month hyperscale pause is expected at a future meeting.
Latest news: September 9, 2026