Glossary

As of October 2026

Terms taken from Iowa county data center ordinances and from the phrases supervisors are using while they draft. A few industry terms that come up next to those rules are included and labeled as such. When adopted-ordinance texts for the other counties are added, this list should pick up any new defined words.

Abatement
A local cut in the property tax on a project for a set number of years. Waukee's 2017 agreement with Apple is a 20-year abatement on the buildings, with a minimum taxable value per building. Industry term used in Iowa development agreements, not a zoning definition. City of Waukee.
Accessory use
Equipment that serves some other main use, such as a server closet in an office. Jefferson County's definition of a data center facility excludes that kind of incidental equipment when it stays under the power or water threshold. Jefferson County ordinance text.
Average hourly noise level
Linn County's sound standard. It is the average level over an hour, measured at the outer wall of an occupied building, in both dBA and dBC. It does not count the background sound already there. Linn County ordinance.
Backup generator
A standby generator that runs if grid power fails, and during tests. Linn County requires a backup-power plan covering fuel, the number and size of units, testing, noise, emissions, and the permits those units need. Linn County ordinance.
Battery energy storage system (BESS)
Jefferson County defines this as equipment that stores electricity and later sends it back out, including the batteries, enclosures, cooling, and fire suppression. Several Iowa moratoriums cover battery storage along with data centers. Jefferson County ordinance text.
Closed-loop cooling
A cooling system that recirculates the same coolant, like a car radiator, instead of evaporating a continuous supply of water. Jefferson County requires it unless the board approves something else. Evaporative cooling, which uses water to carry heat away, is what West Des Moines Water Works says several Microsoft buildings use. Evaporative cooling is the utility's description, not a term defined in these ordinances. Jefferson County ordinance text.
Conditional use
A use the county allows only after a special review, not by right. Allamakee County allows a data center over 3 megawatts only as a conditional use in the I-2 district. Warren County allows a data center only as a conditional use in the HI district. Allamakee County Amendment 20.
Colocation
A data center that rents space and power to more than one customer. Industry term. It is not defined in the county ordinances reviewed here. Boone's current proposal is described in the news as a small colocation project. KWBG, October 6, 2026.
Cryptocurrency mining
Computers used to validate transactions and earn digital currency. Jefferson County treats a cryptocurrency mining operation as a data center. Jones County regulates cryptocurrency facilities and data centers in the same zoning article. Jones County ordinance.
Data center
Linn County defines it as one or more buildings used mainly to store, manage, process, and transmit digital data, including cryptocurrency mining. Jefferson County's parallel term, "data center facility," adds cloud, high-performance, and artificial-intelligence computing, and excludes an ordinary office server room. Linn County ordinance.
Data center campus
Jefferson County's term for one or more buildings planned or run as one project, including later phases. Shared power, cooling, access, or ownership is enough to count them together. Separate meters or company names do not split them apart. Jefferson County ordinance text.
Decommissioning
Taking a data center out of service and restoring the site. Jefferson County requires a decommissioning and site-reclamation plan, a cost estimate, and financial assurance such as a bond or letter of credit, updated at least every five years. Jefferson County ordinance text.
Development agreement
A contract between the company and the city or county, often covering jobs, infrastructure, and payments. Linn County requires an economic development agreement for large-scale projects. The dollar terms of those agreements are not in the zoning text. Linn County.
Electrical design capacity
Jefferson County's term for the maximum electrical load, in megawatts, that the campus is designed to draw in normal operation, from the utility, on-site generation, or both. Planned later phases count toward the total. Jefferson County ordinance text.
Full-cutoff fixture
An outdoor light aimed so it does not shine upward. Linn County and Jefferson County both require full-cutoff fixtures and say the light may not spill onto neighboring property. Linn County ordinance.
Hyperscale
Industry shorthand for a very large cloud or artificial-intelligence campus. The City of Dubuque, not a county code, defined it for a moratorium as 100,000 square feet or more, more than 75 megawatts, 5,000 or more servers, or more than 50 gallons of water a minute. Counties in the ordinances above more often say "large-scale" or "regulated." City of Dubuque.
Interconnection
The point where the data center ties into the electric grid. Jefferson County asks applicants to show grid interconnection points on the site plan. A substation, the fenced yard of transformers that changes voltage, is the usual industry name for that equipment. "Substation" is not defined in the ordinances reviewed here. Jefferson County ordinance text.
Large-scale data center
Linn County: a data center designed for more than 20 megawatts, or that uses more than 50 gallons of water a minute on an annualized basis. Buildings in one campus are added together. Linn County ordinance.
Micro data center
Allamakee County's term for a data center of 3 megawatts or less. Those may be allowed with a permit in the A-1, C-1, I-1, and I-2 districts. A center over 3 megawatts is treated as large and is limited to a conditional use in I-2. Allamakee County Amendment 20.
Megawatt (MW)
A unit of electric power. One megawatt is 1,000 kilowatts. Iowa ordinances use it as a size test: Jefferson County regulates a campus above 5 megawatts of electrical design capacity, and Linn County treats more than 20 megawatts as large-scale. Jefferson County ordinance text.
Moratorium
A temporary county ban on accepting new data center applications, usually while an ordinance is written. It is adopted by resolution or ordinance and has an end date or a condition that ends it. It is not itself the permanent zoning rule. Iowa County minutes, July 31, 2026.
Occupied building
Jefferson County uses this for the buildings a project is measured against. It includes a home, school, hospital, church, library, or other public gathering place in use when the application is filed, and buildings that house livestock. Jefferson County ordinance text.
Place of public assembly
Linn County's list of gathering places used for the 1,000-foot setback: retirement and nursing homes, schools, child care, group homes, hospitals, detention facilities, and human-service facilities. Accessory uses to the data center itself do not count. Linn County ordinance.
Power usage effectiveness (PUE)
An industry ratio of total facility power to the power used by the computers. Lower is more efficient. It is not defined in the Iowa ordinances reviewed here, and a low PUE does not by itself mean the building uses little electricity.
Project area
Jefferson County's term for every parcel, road, utility, and staging area the project will use, whether owned or leased. Jefferson County ordinance text.
Regulated data center
Jefferson County: a data center facility or campus with electrical design capacity above 5 megawatts, counting planned phases together. Below that, the chapter's data center rules do not apply. Jefferson County ordinance text.
Road use agreement
A county contract that names the roads construction trucks will use and who repairs them. Linn County requires one before construction. Jefferson County's version can include dust control, overweight loads, and financial security. Linn County ordinance.
Small-scale data center
Linn County: 20 megawatts or less, and less than 50 gallons of water a minute on an annualized basis. The whole campus is counted together. Linn County ordinance.
Special use permit
Jones County's approval for a data center or cryptocurrency facility in the agricultural, commercial, and industrial districts where the use is allowed. A site plan is required first. Jones County ordinance.
Stormwater pollution prevention plan
The construction-site plan for keeping soil and other pollutants out of ditches and streams. Linn County requires one, along with a stormwater management plan and an erosion-control plan. Linn County ordinance.
Tax increment financing (TIF)
A city tool that uses the new property tax from a site to pay for improvements there. Cedar Rapids' Google project sheet says that if a state jobs-program exemption is not approved, the city would look at a comparable TIF rebate. Industry and municipal term, not a zoning definition. City of Cedar Rapids FAQ.
Water-use impact statement
Clinton County requires this filing before a data center can get a special exception permit. The same ordinance requires closed-loop liquid cooling and a decommissioning plan. Clinton County zoning ordinance.
Water use agreement
A written deal on how much water the project may use and how that use is reported. Linn County requires one for large projects. Jefferson County's version also covers drought, interference with existing users, and the water provider when there is one. Linn County.
Water usage effectiveness (WUE)
An industry measure of water used per unit of computing energy. It is not defined in the Iowa ordinances reviewed here. A county rule that sets gallons per minute, as Linn County does, is a different kind of limit.